How Much Concrete Do I Need? A UK Site Guide (2026)
Concrete is the one material you really do not want to get wrong. Order short and you have a cold joint, a part-load surcharge and a gang stood waiting on a second wagon. Order long and you are paying for concrete you are barrowing into a skip. Here is how to work out the volume properly, the way it is done on site.
Start with the volume
Concrete is ordered by volume in cubic metres (m³), so every calculation comes back to length × width × depth — all in metres. The most common slip is mixing your units: a slab measured in metres but a thickness quoted in millimetres. Convert the thickness to metres first (100mm = 0.1m) and the rest falls into place.
If you would rather skip the arithmetic, put your dimensions into the Site Works concrete calculator and it will give you the volume plus an estimate of 20kg ready-mix bags for smaller pours.
Step 1: work out the volume
For a slab or base, it is length × width × thickness. A slab 5m × 4m at 150mm thick is:
- 5 × 4 × 0.15 = 3.0 m³
For a strip footing, it is length × width × depth. For a column or pad, it is the plan area × depth. Add separate elements together for the total pour.
Step 2: add a waste and over-dig allowance
Ground is never as neat as the drawing. Trenches over-dig, formwork bulges, levels vary and some concrete is always lost in handling. As a working rule:
- 5% for a clean, formed pour on a hard, accurate dig.
- 10% for trench fill and footings where the ground is uneven.
So that 3.0 m³ slab becomes around 3.15 to 3.3 m³ once you allow for waste. With ready-mix it is usually worth rounding up to the nearest quarter metre, because a second part-load is expensive.
Ready-mix or mix on site?
For anything over about a cubic metre, ready-mix delivered by wagon is almost always cheaper and better quality than mixing on site. Below that, bagged ready-mix or a site mixer makes sense. As a rough guide a 20kg bag of ready-mix gives around 0.009 to 0.01 m³ once mixed — so roughly 100 bags to the cubic metre, which is a lot of mixing. The crossover where a wagon pays for itself comes quickly.
Get the mix right
When you order ready-mix you will be asked for the strength, usually given as a C grade — C20/25, C25/30, C30/37 and so on. As a rough steer:
- C20/25 — general fill, blinding, non-structural work.
- C25/30 — most domestic foundations and slabs.
- C30/37 — structural slabs, heavier loadings, durability where specified.
Always work to the engineer's specification where there is one. If in doubt, ask — the batching plant would rather get the order right than send the wrong mix.
A quick worked example
Say you are pouring a garage base 6m × 3m at 150mm, with a thickened edge that adds roughly 0.2 m³:
- Slab: 6 × 3 × 0.15 = 2.7 m³
- Thickened edge: 0.2 m³
- Total: 2.9 m³
- Add 10%: round up to 3.25 m³
That is one clean wagon load rather than gambling on 3.0 and hoping.
Don't forget the pour-day kit
Concrete arrives whether you are ready or not, so have the gear on site the day before — barrows, rakes, a poker or beam for compaction, floats, edging tools, polythene for curing and enough bodies to move it before it goes off. A pour that arrives faster than you can place it is a bad day.
The bottom line
Volume in metres, length × width × depth, add 5 to 10% for waste, round up to the nearest quarter metre for ready-mix, and order the right strength for the job. Two minutes with a tape and a calculator saves the part-load that wipes out your margin.
Estimates here are for guidance. Always work to the structural engineer's design and check against your own setting-out before placing a large order.